Construction Updates

The construction of Raksha Towers at Greater Noida West (Noida Extension) is going on at full swing with a concerted effort to complete and deliver the project well within the stipulated time frame. Our engineers and staff are working relentlessly to ensure the timely delivery, while at the same time maintaining the quality of construction as per the prescribed standards and norms. Following are the latest photographs of the construction site :

May Construction Update

TOWER A

Raksha Tower Raksha Tower

Structure of Tower A completed, with brickwork going on 17th and 18th floors, and railing work complete till 15th floor.28th May 2016

TOWER B

Raksha Tower Raksha Tower

Also construction of 7 floors of Tower B has been completed, and work started on the 9th floor.28th May 2016.

TOWER C

Raksha Tower

Work started on the 1th floor-28th May 2016.

April Construction Update

TOWER A

Raksha Tower Raksha Tower

Structure of Tower A completed, with brickwork going on 17th and 18th floors, and railing work complete till 15th floor. Moreover, plaster work is going on the 13th and 14th floors.22th April 2016

TOWER B

Raksha Tower Raksha Tower Raksha Tower

Also construction of 6 floors of Tower B has been completed, and work started on the 8th floor. 22th April 2016.

TOWER C

Raksha Tower Raksha Tower

Upper basement work completed -22th April 2016.