The construction of Raksha Towers at Greater Noida West (Noida Extension) is going on at full swing with a concerted effort to complete and deliver the project well within the stipulated time frame. Our engineers and staff are working relentlessly to ensure the timely delivery, while at the same time maintaining the quality of construction as per the prescribed standards and norms. Following are the latest photographs of the construction site :

Construction Updates: September

TOWER A

Raksha Tower Raksha Tower Raksha Tower Raksha Tower

Structure, brickwork and railing work of Tower A completed. External Plaster as well as finishing work started. 7th September 2016

TOWER B

Raksha Tower Raksha Tower Raksha Tower

Construction of 10 floors of Tower B has been completed, and work started on the 11th floor. Brickwork going on 4th floor. 7th September 2016.

TOWER C

Raksha Tower Raksha Tower Raksha Tower

Construction of 5 floors of Tower C has been completed, and work started on the 6th floor. 
7th September 2016
.

August Construction Update

TOWER A

Raksha Tower Raksha Tower Raksha Tower

Structure, brickwork and railing work of Tower A completed. External Plaster as well as finishing work started. 6th August 2016

TOWER B

Raksha Tower Raksha Tower

Construction of 9 floors of Tower B has been completed, and work started on the 10th floor. Brickwork going on 4th floor. 6th August 2016.

TOWER C

Raksha Tower Raksha Tower

Construction of 4 floors of Tower C has been completed, and work started on the 5th floor. 
6th August 2016
.

July Construction Update

TOWER A

Raksha Tower Raksha Tower Raksha Tower Raksha Tower

Structure, brickwork and railing work of Tower A completed. External Plaster and interior finishing work started. 6th July 2016

TOWER B

Raksha Tower Raksha Tower

Also construction of 8 floors of Tower B has been completed, and work started on the 9th floor. Brickwork going on 2th floor. 6th July 2016.

TOWER C

Raksha Tower Raksha Tower

Also construction of 3 floors of Tower C has been completed, and work started on the 4th floor. 6th July 2016.